Reconstruction work will take place on Mississauga Road, from Queen Street West to Beechgrove Sideroad.

Some of the work includes adding gravel and grading on shoulders, culvert replacement and ditching, asphalt paving, traffic line painting and more. This will help improve road safety, accommodate increased traffic and improve road drainage.

A full road closure is expected.  Designated detour route will be Beechgrove Sideroad, Shaws Creek Road and Highpoint Sideroad.  Local access will be maintained.  

May 18, 2020 (anticipated start date)

July 17, 2020 (anticipated end date)